Chih-Deh Factory – Double-Sided Wall Formwork     

INFORMATION

Project:Chih-Deh Factory – Double-Sided Wall Formwork

Location:Taiwan, Tainan

Description:For the Chih-Deh factory construction, Sucoot supplied a double-sided wall formwork system capable of achieving fair-faced concrete finishes — eliminating the need for secondary surface treatment after stripping. The system uses form ties to withstand lateral casting pressure and inclined struts to maintain wall verticality during pouring. Combined with Sucoot’s Ring Lock Scaffolding System, a stable working platform was built to lift and reposition the wall formwork for higher wall construction in subsequent levels, ensuring both precision and efficiency.

Challenges

Sucoot's Solutions

Engineering Data

Year of Construction
2018
Length (m)
40M
Height (m)
5.4M
Thick (cm)
X/ 20CM
Supporting Range
Partition
Formwork Range
Factory wall
Cycle Time
Divided into sectional works