Taoyuan Airport MRT – Contract CE02
INFORMATION
Project :Taoyuan Airport MRT – Contract CE02
Location :Taiwan, Taoyuan
Description :In the Taoyuan Airport MRT CE02 section, Sucoot’s Ring Lock Scaffolding System was applied to support large bridge spans with exceptional efficiency and safety. The system allowed entire shoring towers to be lifted and relocated as a whole, eliminating repetitive dismantling and reassembly. Using only 10 sets of materials and a 7-person crew, the contractor successfully completed 300 spans in two years — on schedule, on quality, and with zero safety incidents.
Challenges
01
The long-distance span-by-span casting required extensive time and materials, demanding a balance between construction efficiency and cost effectiveness.
02
Maintaining consistent quality and alignment across hundreds of bridge segments.
Sucoot's Solutions
01
Adopted Sucoot’s heavy-duty Ring Lock Scaffoldings with crane-lift relocation capability
02
Replaced traditional dismantle-and-rebuild cycles (5 days) with 0.5-day tower shifts.
03
Achieved high precision, faster turnover, and proven field safety over 300 spans in two years with 10 sets of materials and a crew of 7 workers.