Taoyuan MRT-CE02
INFORMATION
Project:Taoyuan MRT-CE02
Type:Railway Bridge
Contractor:Kung Sing Engineering Corporation
Owner:Bureau of High Speed Rail, MOTC
Description:Total 300 spans, there are 12 sets material, took total 24 months to complete.
Engineering Data
| Year of Construction |
2009~2013 |
| Bridge Length (m) |
10500M |
| Bridge Width (m) |
10M |
| Bridge Height (m) |
6~18M |
| Supporting Range |
Upper Structure for Bridge |
| Cycle time |
2 spans/month |
| Description |
Total 300 spans, there are 12 sets material, took total 24 months to complete. |