Taoyuan MRT-CE02     

INFORMATION

Project:Taoyuan MRT-CE02

Type:Railway Bridge

Contractor:Kung Sing Engineering Corporation

Owner:Bureau of High Speed Rail, MOTC

Description:Total 300 spans, there are 12 sets material, took total 24 months to complete.

System:
Ø60.2 T:3.2mm Shoring (Heavy Duty) Scaffolding

Engineering Data

Year of Construction
2009~2013
Bridge Length (m)
10500M
Bridge Width (m)
10M
Bridge Height (m)
6~18M
Supporting Range
Upper Structure for Bridge
Cycle time
2 spans/month
Description
Total 300 spans, there are 12 sets material, took total 24 months to complete.